Plan Reviews

The Building and Safety Division is legally required to approve the building in the design stage before issuance of any permit for construction. In order to approve the design, it becomes necessary, therefore, to conduct a formal, detailed plan review to verify compliance with applicable codes.

Once the plans are accepted for review, they are placed in line for initial plan review based on a first-come-first-serve basis. There are, however, some exceptions for ‘quickie,’ counter review, fast track, and expedited plan reviews. For details, refer to Plan Review Services below.

When the plans are reviewed, a correction letter is prepared and plans are marked in red ink where corrections are needed. Plans and related documents are picked up by the contact person for corrections. After the corrections are made by the owner/agent, plans are accepted for a second plan review, and they are placed in the resubmittal line on a first-come-first-serve basis.

At the second review, if the plans are in compliance with the corrections requested, they are approved. If there are still undone corrections, a second review correction letter is prepared by the plan checker. Thus, the plans go back and forth in the system till they are approved.

Plan Review Services:

Regular Plan Review is done on a first-come-first-serve basis. Turnaround time varies from 4-5 weeks for new submittals to 2-3 weeks for resubmittals. Plan Check turnaround times may vary depending on the volume of work. To check the plan check status, please visit our Citizen Access Portal. https://vcca.ventura.org/.“

Fast Track for Non-Residential Building Only:

(Subject to Building Official Approval)

With a surcharge of 35% over basic plan check fee, plans are accepted in three phases.

Handout “B-2” shall be used as a primary guide, and requirements of each phase shall be:

PHASE I (Foundation Only Permit)

PHASE II (Structural Shell Only)

PHASE III (Tenant Improvements)

  • All site work plans, including underground plumbing, mechanical and electrical work.
  • Foundation plans and structural calculations for the entire building.
  • Plan check and permit fees shall be 35% of total fees.
  • Complete structural plans and calculations shall be submitted for the structure above the foundation.
  • The location and details of all bearing walls, firewalls, occupancy separation walls, and area separation walls shall be submitted.
  • Plan check and permit fees shall be 45% of total fees.
  • Complete architectural, structural, plumbing, mechanical, and electrical plans and all required energy calculations shall be submitted.
  • Location and details of all handicapped accessibility features shall be shown on the plans.
  • All corridors, stair shafts, and other existing features shall be clearly shown and detailed.
  • Plan check and permit fees shall be 20% of total fees.

IPC Inspector Plan check for Minor Residential Additions and U Occupancies:

Drawings for one-story residential additions of conventional construction will normally be reviewed by the building inspector rather than the plan check staff.
Plans shall contain sufficient information to show compliance with basic code requirements. Refer to handout “B-1” for specific requirements. Additions involving engineering calculation and two-story additions shall be referred to plan check staff.

Examples of what qualify as IPC are:

  • One story room additions less than 1,000 square feet (non-engineered).
  • Patio covers, carports, garages (non-engineered) except for those utilizing Building and Safety preapproved “handout” sheets, which will be issued over the counter.
  • One-story pool house/recreation buildings less than 1,000 square feet (non-engineered).
  • Decks (non-engineered).
  • Revisions to plans where no engineering is involved.
  • Mobile home foundations, if Counter Staff is unable to issue permit over-the-counter.
  • “Granny flats” (one story, conventional construction, 700 square feet maximum, detached).

Different types of plan reviews:

  • Building: Includes life safety, structural, handicap accessibility, and energy conservation.
  • Plumbing: Includes plumbing lines, water heaters, water closets, sinks, and lavatory, etc.
  • Mechanical: Includes furnace, condenser, wall heaters, chillers, and duct workers, etc.
  • Electrical: Includes electrical wiring, panel sizing, electrical equipment, etc.

Information on minimum requirements on my plans:

Plan-Check Staff Availability:

  • Plan review Engineer availability is 8:00 am-4:00 pm; appointment required for in-person meeting.

Translate Disclaimer

The vcrma.org website has been translated for your convenience using translation software powered by Google Translate. Reasonable efforts have been made to provide an accurate translation, however, no automated translation is perfect nor is it intended to replace human translators. Translations are provided as a service to users of the Ventura.org website, and are provided “as is.” No warranty of any kind, either expressed or implied, is made as to the accuracy, reliability, or correctness of any translations made from English into any other language. Some content (such as images, videos, Flash, etc.) may not be accurately translated due to the limitations of the translation software.

The official text is the English version of the website. Any discrepancies or differences created in the translation are not binding and have no legal effect for compliance or enforcement purposes. If any questions arise related to the accuracy of the information contained in the translated website, please refer to the English version of the website which is the official version.