Planning Director Decisions |
Avg. # of Days to Deem Application Complete |
Goal | % On Time |
Avg. # of Days from Env. Review to Approval |
Goal | % on Time |
Avg. Cost |
CUP- Residential &Accessory Uses |
118 | 30 | 50% | 155 | 60 | 0% | $28,500 |
CUP- Agricultural and Accessory Uses | 68 | 30 | 33% | 137 | 60 | 44% | $24,400 |
CUP- Commercial & Industrial | 43 | 30 | 54% | 135 | 60 | 17% | $20,200 |
CUP- Wireless Facilities | 79 | 30 | 33% | 108 | 60 | 18% | $11,000 |
Major Modification | 87 | 30 | 50% | 154 | 60 | 25% | $32,500 |
Minor Modification | 63 | 30 | 28% | 154 | 60 | 25% | $14,500 |
Wireless Facility Modification | 40 | 30 | 53% | 105 | 60 | 27% | $14,300 |
Standard Permit Adjustment | 43 | 30 | 54% | 24 | 60 | 90% | $2,500 |
Minor Permit Adjustment | 33 | 30 | 85% | 15 | 60 | 87% | $1,400 |
Parcel Map | 45 | 30 | 33% | 279 | 60 | 17% | $28,200 |
Planned Developement- Residential | 61 | 30 | 50% | 133 | 60 | 27% | $17,700 |
Planned Development- SRP Overlay Zone | 60 | 30 | 0% | 58 | 60 | 20% | $17,300 |
Planned Development-Commercial | 44 | 30 | 33% | 92 | 60 | 33% | $25,000 |
Specific Types |
Avg. # of Days to Deem Application Complete |
Goal | % On TIme |
Avg. # of Days from Env. Review to Approval |
Goal | % On Time | Avg. Cost |
Agricultural Operations | 51 | 30 | 30% | 106 | 60 | 35% | $11,100 |
Wireless Communications Facilities | 47 | 30 | 52% | 81 | 60 | 44% | $10,000 |
Dwellings | 50 | 30 | 32% | 91 | 60 | 33% | $12,000 |
Festivals, Animal Shows, Temporary Events | 43 | 30 | 45% | 116 | 60 | 27% | $12,800 |
Contractor Storage Yards | 31 | 30 | 43% | 41 | 60 | 86% | $10,800 |
Exempt Projects |
Avg. # of Days to Deem Application Complete |
Goal | % On Time |
Avg. # of Days from Exemption Determination to Approval |
Goal | % on Time |
Avg. Cost |
CUP- Agricultural and Accessory Uses |
56 | 30 | 0% | 60 | 60 | 100% | $8,300 |
CUP- Commercial & Industrial | 30 | 30 | 100% | 322 | 60 | 0% | $15,800 |
CUP- Wireless Facilities | 42 | 30 | 41% | 127 | 60 | 12% | $7,500 |
Major Modification | 43 | 30 | 0% | 456 | 60 | 0% | $9,600 |
Minor Modification | 50 | 30 | 24% | 191 | 60 | 13% | $10,000 |
Wireless Facility Modification | 65 | 30 | 55% | 116 | 60 | 18% | $12,400 |
Standard Permit Adjustment | 54 | 30 | 49% | 21 | 60 | 86% | $1,700 |
Minor Permit Adjustment | 61 | 30 | 57% | 7 | 60 | 100 | $1,800 |
Parcel Map | 60 | 30 | 0% | 99 | 60 | 0% | $46,800 |
Planned Development-Commercial | 44 | 30 | 20% | 75 | 60 | 40% | $9,200 |
Projects Requiring a Negative Declaration |
Avg. # of Days to Deem Application Complete |
Goal | % On Time |
Avg. # of Days from Envrionmental Determination to Approval |
Goal | % on Time |
Avg. Cost |
CUP- Agricultural and Accessory Uses |
68 | 30 | 27% | 202 | 180 | 55% | $24,900 |
CUP- Commercial & Industrial | 51 | 30 | 43% | 151 | 180 | 71% | $12,800 |
CUP- Wireless Facilities | 99 | 30 | 17% | 106 | 180 | 100% | $17,100 |
Major Modification | 161 | 30 | 0% | 337 | 180 | 50% | $41,100 |
Minor Modification | 61 | 30 | 39% | 151 | 180 | 70% | $16,300 |
Wireless Facility Modification | 84 | 30 | 33% | 212 | 180 | 67% | $15,800 |
Standard Permit Adjustment | 35 | 30 | 52% | 29 | 180 | 96% | $2,900 |
Minor Permit Adjustment | 42 | 30 | 60% | 20 | 180 | 100 | $1,600 |
Parcel Map | 57 | 30 | 33% | 343 | 180 | 0% | $22,200 |
Planned Development-Commercial | 43 | 30 | 50% | 295 | 180 | 0% | $23,500 |
Housing Projects (Exempt) |
Avg. # of Days to Deem Application Complete |
Goal | % On Time |
Avg. # of Days from Exemption Determination to Approval |
Goal | % on Time |
Avg. Cost |
CUP- Residential & Accessory Uses | 118 | 30 | 0% | 155 | 60 | 0% | $16,120 |
Planned Development- Residential | 56 | 30 | 43% | 122 | 60 | 29% | $11,250 |
Planned Development- SRP Overlay | 33 | 30 | 0% | 21 | 60 | 100% | $7,700 |